Persediaan Spare Part Menggunakan Reliability Centered Spares Dan inventory Analysis Di CV. selorejo Bantul

Authors

  • Aprilia Hardiyanti Institut Sains & Teknologi AKPRIND Yogyakarta
  • Imam Sodikin Institut Sains & Teknologi AKPRIND Yogyakarta
  • Rahayu Khasanah Institut Sains & Teknologi AKPRIND Yogyakarta

DOI:

https://doi.org/10.34151/rekavasi.v10i2.4246

Keywords:

Criticality Index, Inventory Analysis, Poisson Process, Reliability Centered Spares

Abstract

The results obtained from the RCS worksheet show that there is 1 unit of high critical category component, 10 units of medium critical category component and 4 units of low critical category component. Calculation of component requirements for the next 12 months using the Poisson process obtained the total requirement for 4 months of critical component spare parts to be able to meet 95% availability of v-belt mixers is 7 units (12 months = 21 units), hydraulic rubber requires 4 units (12 months=12 units), and vibrating v-belt system requires 2 units (12 months = 6 units). Order size and costs incurred for 4 months for 7 units of v-belt mixer component spare parts of IDR 569,500 (12 months = IDR 1,708,500), 4 units of hydraulic rubber components IDR 653,800 (12 months = IDR 1,961,400) and a v-belt system component of 2 units of IDR 103,300 (12 months = IDR 309,900). The total inventory cost for the 12 months that the company has to pay for the three critical component spare parts is IDR 3,979,800.

Author Biographies

Imam Sodikin, Institut Sains & Teknologi AKPRIND Yogyakarta

 

 

Rahayu Khasanah, Institut Sains & Teknologi AKPRIND Yogyakarta

 

 

Downloads

Published

2022-12-30

Issue

Section

Articles